July 08, 2019

TRAFFIC CONTROL AND SAFETY

  • No traffic issues to report

PROGRESS SINCE May 2, 2019

  • Milling and overlay is complete

  • All concrete curbs, bump outs, gutter pans, and sidewalks are complete

  • Sandblasting of specialty concrete is complete

  • Final striping is ongoing and should be complete 

  • Planting soil installation and mulch placement is ongoing

  • Signage installation is ongoing

  • Installation of remaining benches and bike racks is on going

  • All known damaged concrete has been replaced

  • Concrete infill at Oklahoma is complete
     

TWO-WEEK LOOK AHEAD

  • Complete remaining work, clean up and demobilize

May 20, 2019

TRAFFIC CONTROL AND SAFETY

  • Expect occasional lane closures for milling and paving operations. Traffic will be maintained by flagging or detours.

PROGRESS SINCE May 2, 2019

  • Milling and overlay from Depot to Baxter is complete

  • Driveway at 1221 N Central has been removed and replaced with sidewalk

  • All concrete on south side of Baxter is completed 

  • Curbs on north side of Baxter 50% complete

  • Median island curbs from Pearl to end of project are complete

  • Island at 1306 North Central was pulled back to allow driveway access

  • Dig outs are complete from Baxter to Oklahoma

TWO-WEEK LOOK AHEAD

  • Mill and overlay Central from Baxter to end of project

  • Continue work on the north side of Baxter

  • Dig outs from Oklahoma to end of project

May 02, 2019

TRAFFIC CONTROL AND SAFETY

  • Expect occasional lane closures for milling and paving operations. Traffic will be maintained by flagging or detours.

PROGRESS SINCE April 4, 2019

  • Driveway and loading dock entrance at Three Rivers Market are complete

  • Curbs, sidewalks, bench pads, and gutter pans on south side of Baxter are 90% complete

  • Median islands from Bearden to Pearl are complete

  • Milling from Depot to Bernard is complete

  • Dig outs done from Depot to Bernard

  • Excavation on the north side of Baxter is ongoing

TWO-WEEK LOOK AHEAD

  • Complete work on the south side of Baxter

  • Begin work on the north side of Baxter

  • Complete milling from Bernard to Baxter

  • Dig outs from Bernard to Baxter

  • Pave from Depot to Baxter

April 04, 2019

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

PROGRESS SINCE March 7, 2019

  • Interconnect cable installation is ongoing

  • Southwest corner of Baxter Avenue has been poured

  • Curbs and sidewalks on the east side of N Central have been poured from Anderson to Baxter

  • Bus pad on Central at Three Rivers Market has been poured

  • Large bump out at the northeast corner of Baxter has been poured

  • Asphalt patching along Central is complete

  • Benches on North Central have been installed except for benches at the Knox County Central building

  • Excavation on the south side of Baxter is ongoing

TWO-WEEK LOOK AHEAD

  • Begin work on the north side of Baxter Avenue

March 07, 2019

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

PROGRESS SINCE Feb. 22, 2019

  • Bike racks on Central have been installed

  • Above-grade planters have been installed

  • Interconnect cable installation is ongoing

  • Curbs and sidewalks on the west side of N Central have been poured from Anderson to Baxter

  • Driveway at 1121 N Central has been poured

  • Southwest corner of Baxter has been poured

  • Planting beds have been cleared of trash, existing weeds have been sprayed, and pre-emergent has been applied

TWO-WEEK LOOK AHEAD

  • Begin work on the south side of Baxter Avenue

February 21, 2019

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

PROGRESS SINCE Feb. 7, 2019

  • Old signal pole and sign pole on the north side of West Anderson have been removed

  • Pedestrian signal at Bernard is now active

  • Curbs, sidewalks, and ramps on both sides of West Anderson have been poured

  • Asphalt removal and grading for bump-outs between Anderson and Baxter has begun

TWO-WEEK LOOK AHEAD

  • Complete curbs, bump outs, and driveways on the west side of N Central Street working toward Baxter Avenue

February 07, 2019

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

 

PROGRESS SINCE Jan. 25, 2019

  • Curbs, sidewalks, ramps, and bus shelter pad on the west side of N Central Street working toward Baxter have been poured

  • New signals at Anderson have been activated

  • Planting soil on the east side of Central has been placed to Scott Avenue.

TWO-WEEK LOOK AHEAD

  • Continue curbs, bump outs, and driveways on the west side of N Central Street working toward Baxter Avenue

January 25, 2019

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

 

PROGRESS SINCE Jan. 10, 2019

  • Curbs, sidewalks, ramps, and bus shelter pad on the west side of N Central Street working toward Baxter are up to date

  • De-mobilizing from laydown yard

TWO-WEEK LOOK AHEAD

  • Continue curbs, bump outs, and driveways on the west side of N Central Street working toward Baxter Avenue

  • Resume work on signal system at Anderson 

January 10, 2019

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

 

PROGRESS SINCE Dec. 13, 2018

  • Curbs, bump outs, and driveways on east side of Central between Anderson and Scott have been poured

  • Asphalt  has been patched on the east side of Central between Anderson and Scott

  • Signal cabinet has been relocated and the new signals have been activated at Bernard

  • Signal pull box at Baxter has been relocated

TWO-WEEK LOOK AHEAD

  • Curbs, bump outs, and driveways on the west side of Central starting at Scott and working back toward Baxter

  • KAT shelter at 1401 Central will be removed by 1/14/19

  • Resume work on signal system at Anderson once KUB overhead work is complete

December 13, 2018

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

 

PROGRESS SINCE Nov. 29, 2018

  • Curbs, bump outs, and driveways between Baxter and Anderson on the east side of Central have been poured

  • Bump out and sidewalks on both sides of East Anderson have been poured

  • The large bump-out/sidewalks at the southeast corner of Baxter have been poured

  • New signal activated at Broadway

TWO-WEEK LOOK AHEAD

  • Continue to work toward activating new signals at Bernard, cabinet pedestal is being relocated

  • Work on curbs and sidewalks on North Central until design issues on Baxter are resolved and overhead utility relocations are completed

  • SCI will work four-day weeks after Christmas and New Year's, weather dependent

November 29, 2018

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

 

PROGRESS SINCE Nov. 13, 2018

  • Bench pad closest to Baxter Avenue on the east side of North Central has been removed and the sidewalks have been re-poured

  • Radius curbs at southeast corner of Baxter Avenue have been poured to 20' radius

  • The large bump-out/sidewalks at the southeast corner of Baxter have been poured

  • New signal mast arms installed at Broadway

  • New signals activated at 5th intersection

  • Bump-out curbs at East Anderson have been poured

 

TWO-WEEK LOOK AHEAD

  • Continue to work toward activating new signals at Broadway, Bernard and Anderson

  • Work on curbs and sidewalks on North Central 

November 13, 2018

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

 

PROGRESS SINCE Nov. 1, 2018

  • Bench pad closest to Baxter Avenue and sidewalks south of Baxter have been removed

  • Radius curbs at southeast corner of Baxter Avenue have been formed to 20' radius

  • New signal mast arms installed at 5th and Bernard

  • All new pedestrian signal poles are installed

  • New traffic signal at Baxter Ave. is complete

 

TWO-WEEK LOOK AHEAD

  • Continue to work toward activating new signals at 5th, Broadway, Bernard and Anderson

  • Place planting soil on south side of Baxter Ave.

  • Work on curbs, sidewalks, and bench landings on south side of Baxter Ave.

November 01, 2018

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

 

PROGRESS SINCE Oct. 18, 2018

  • KUB has completed work to relocate the gas line in Baxter Ave.

  • Planting soil has been placed to Baxter Ave.

  • Storm drainage work on Baxter Ave. is complete

  • All storm drainage work is complete

  • New traffic signal at Baxter Ave. is complete

 

TWO-WEEK LOOK AHEAD

  • Continue to work toward activating new traffic signals at 5th, Bernard and Anderson

  • Place planting soil on south side of Baxter Ave.

  • BEgin work on curbs, sidewalks, and bench landings on south side of Baxter Ave.

October 18, 2018

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.

 

 

PROGRESS SINCE Oct. 4, 2018

  • KUB is continuing to relocate the gas line at Baxter Ave.

  • Curbs and sidewalks have been poured to halfway between Pearl Place and Baxter Ave.

  • Planting soil has been placed from Bearden Place to Pearl Place and is currently being placed for Knox County Building to Baxter Ave.

  • Storm drainage work on Baxter Ave. has resumed

  • Progression is flying arms at Baxter and Anderson avenues

  • Change order storm at Three Rivers Market has been installed
     

TWO-WEEK LOOK AHEAD

  • Signal system infrastructure work continues across the project

  • Complete curbs, sidewalks and bench landings from Knox County Building to Baxter Ave.

  • Complete storm work in Baxter Ave.

October 04, 2018

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.
     

 

 

PROGRESS SINCE Sept. 24, 2018

  • KUB has begun relocating the gas line at Baxter Ave.

  • Curbs and sidewalks across Knox County Building have been poured

  • Planters have been excavated from Bearden to Pearl Place

  • Back of the sidewalk planter has been excavated from Knox County Building to Baxter Ave.

  • Total Property Management is placing soil in excavated planters 

  • Progression has been pulling wire at 5th, Broadway, and Bernard
     

TWO-WEEK LOOK AHEAD

  • Signal system infrastructure work at Alexander Avenue

  • Sidewalks and bench landings installed from Knox County Building to Baxter Ave.

  • Resume storm work in Baxter after KUB gas line relocation is complete

September 20, 2018

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.
     

 

 

PROGRESS SINCE Sept. 9, 2018

  • Curbs, sidewalks, driveway, and bus shelter pad in front of All Occasions have been poured

  • Curb cut at Pearl Place has been poured

  • Existing storm at East Scott Avenue has been tied to new storm system

  • Existing storm at All Occasions has been tied in to new storm system

  • Asphalt patching from East Anderson to Oklahoma where new storm was installed 

  • Signal control cabinets have been installed at 5th, Broadway, and Bernard
     

TWO-WEEK LOOK AHEAD

  • Signal system infrastructure work at Alexander Avenue

  • Begin work on curbs and sidewalks from Pearl Place to Baxter

  • Begin excavation for large planting beds from Pearl Place to Baxter Avenue

  • Resume storm work in Baxter after KUB gas line relocation is complete

September 06, 2018

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.
     

 

 

PROGRESS SINCE AUGUST 23, 2018

  • All curbs, sidewalks, and patching in Bernard Avenue intersection is complete

  • Planter curbs from Bernard to Dameron have been poured

  • Driveway for Broadway Restaurant Equipment has been poured

  • Bus shelter pads at Bernard and Dameron have been poured

  • Curbs on east side of Central from Bearden Place to the north entrance to All Occasion Catering have been poured

  • Signal and interconnect infrastructure at Baxter Avenue is complete
     

TWO-WEEK LOOK AHEAD

  • Signal system infrastructure work at Alexander Avenue

  • Curbs, gutter pans, and sidewalks from Pearl Place to Baxter Avenue

  • Resume storm work in Baxter after KUB gas line relocation is complete
     

August 23, 2018

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.
     

 

 

PROGRESS SINCE AUGUST 9, 2018

  • All curbs, sidewalks, and patching in Broadway intersection is complete

  • Regions Bank driveway is complete

  • Central Filling Station driveway is complete

  • Signal and interconnect infrastructures at Baxter Avenue is ongoing
     

TWO-WEEK LOOK AHEAD

  • Complete sidewalks and curbs in Bernard Avenue intersection

  • Complete signal system infrastructure work at Baxter Avenue

  • Curbs, gutter pans, sidewalks, and bus shelter pad from Bernard working toward Dameron
     

August 09, 2018

TRAFFIC CONTROL AND SAFETY

  • No closures at this time.
     

 

 

PROGRESS SINCE JULY 26, 2018

  • All storm drainage in somplete except for Baxter Avenue

  • Signal and interconnect infrastructure in Bernard Avenue is complete

  • Signal poles installed at 5th, Broadway, and Bernard

  • Sidewalks, curbs, and bump outs are complete in Bearden Place intersection

  • Sidewalks at Regions Bank are complete

  • Mock up panels have been poured and reviewed
    a.  Light sandblast finish chosen pending on site confirmation

       b. Newport sand mix chosen over Nolichucky sand mix

  • Mulch installed from 5th Avenue to Bernard Avenue
     

TWO-WEEK LOOK AHEAD

  • Complete sidewalk work at the Broadway intersection

  • Complete driveway at Regions Bank

  • Completed sidewalks and curbs in Bernard Avenue intersection

  • Begin signal system infrastructure work at Baxter Avenue
     

  •  

July 26, 2018

TRAFFIC CONTROL AND SAFETY

  • Closure of East Scott Wednesday, Thursday, and Friday for storm installation
     

 

 

PROGRESS SINCE JULY 12, 2018

  • Storm drainage in West Anderson Avenue is complete

  • Storm drainage at Oklahoma Avenue is complete

  • Bump-out curbs and sidewalks at 5th are complete

  • Signal and interconnect infrastructure in Broadway is complete

  • Sidewalks and bump outs are complete across the food truck park

  • Mock up panels have been poured and will be sandblasted tomorrow
    a.  Aggregate size for specialy concrete mix
    b.  Color difference between Newport sand and Nolichucky sand

     

TWO-WEEK LOOK AHEAD

  • Complete storm drainage in Scott Avenue

  • Complete sidewalk work at the Broadway intersection

  • Sidewalks, gutter pans, and bump outs in the Bearden Place intersection

  • Continue signal system infrastructure work at Bernard Avenue
     

July 12, 2018

TRAFFIC CONTROL AND SAFETY

  • Closure of the westbound right turn lane and shoulder of East Baxter Avenue until mid-July as storm drainage is installed 18-T-0410

  • Daily closures of West Anderson for storm installation, 18-T-0525

     

 

 

PROGRESS SINCE JUNE 28, 2018

  • Storm drainage in East Anderson is complete

  • Storm drainage in West Anderson will be completed this week

  • Bump-out curbs and sidewalks at 5th will be complete this week

  • Signal infrastructure in Broadway intersection will be complete this week
     

TWO-WEEK LOOK AHEAD

  • Resume storm drainage work on east side of Central from Alexander to Oklahoma

  • Begin storm drainage work in Oklahoma

  • Sidewalks, gutter pans, and bump outs from Magpie’s to Bearden Place on the east side of Central

  • Begin signal system infrastructure work at Bernard Avenue

  • Pour mock up panel for enhanced and blasted concrete finishes
     

June 28, 2018

TRAFFIC CONTROL AND SAFETY

  • Closure of the westbound right turn lane and shoulder of East Baxter Avenue until mid-July as storm drainage is installed 18-T-0410

  • Daily closures of east Anderson have been requested for next week for storm installation and asphalt patching.
     

 

 

PROGRESS SINCE JUNE 14, 2018

  • Added storm drainage (C-28 to C-28A) installed at Pearl Place

  • Storm in Baxter installed to C-45, storm work in Baxter currently stopped due to utility conflicts

  • Sidewalks, gutter pans, and bump-outs along the east side of Central are complete to Bernard Avenue

  • Sidewalks, gutter pans, and bump-outs along the east side of Central are complete from Fulton Place to north end of Magpies building
     

TWO-WEEK LOOK AHEAD

  • Install storm drainage in Anderson intersection

  • Resume storm drainage work in East Baxter Avenue once utility conflicts are resolved

  • Sidewalks, gutter pans, and bump outs from Fulton Place to Bearden Place on the east side of Central

  • Complete bump-out curbs and sidewalks at 5th Avenue

  • Continue signal system work at Broadway

  • Pour mock up panel for enhanced and blasted concrete finishes
     

June 14, 2018

TRAFFIC CONTROL AND SAFETY

  • Closure of the westbound right turn lane and shoulder of East Baxter Avenue until mid-July as storm drainage is installed 18-T-0410

  • Closure of East Baxter Avenue this Monday thru Thursday as structure C-41 is set and tied in to existing storm drainage in Central and Baxter 18-0427

     

 

 

PROGRESS SINCE MAY 31, 2018

  • Storm drainage installed from East Baxter to Pearl Place

  • Sidewalks, gutter pans, and bump-outs along the west side of Central are complete from Jennings to mid-block between Pruett Place and Bernard Avenue

  • Signals system infrastructure work, except for the foundation for pole B, is complete at 5th Avenue intersection, remaining pole bases and signal cabinet pedestal will be poured today
     

TWO-WEEK LOOK AHEAD

  • Install storm drainage in East Baxter Avenue

  • Sidewalks, gutter pans, and bump-outs from Fulton Place to Bearden Place on the east side of Central

  • Bump-out curbs and sidewalks at 5th Avenue

  • Continue signal system work at 5th and Broadway intersections
     

May 31, 2018

TRAFFIC CONTROL AND SAFETY

  • Temporary bike detour signage is in place

 

 

PROGRESS SINCE MAY 17, 2018

  • Storm drainage in Bearden Place is complete

  • Storm drainage line “B” is complete (all storm from Depot to Dameron Avenue)

  • Sidewalks along the west side of Central are complete from Broadway to Jennings

  • Bump-outs along east side of Central are complete to Fulton Place

  • Planting soil has been placed from Broadway to Fulton Place

  • Asphalt patching is complete in Bearden Place, across Central/Dameron, and along new curbs to Fulton Place
     

TWO-WEEK LOOK AHEAD

  • Install storm drainage from Baxter to Pearl Place

  • Continue sidewalks, gutter pans, and bump outs from Broadway to Bernard Avenue

  • Complete work on curbs and sidewalks surrounding Broadway intersection

  • Continue signal system work at 5th intersection and at Broadway
     

May 17, 2018

TRAFFIC CONTROL AND SAFETY

  • Traffic control permit in place for closure of Bearden Place this week between Central and Stewart Street.  This work is delayed until KUB can relocate a water main in conflict with the 18' RCP line connecting structures at Stewart Street.

  • Closure of North Central and Dameron Place next week to install storm drainage across North Central and Dameron Place

 

PROGRESS SINCE MAY 3, 2018

  • Storm drainage in Bearden Place is complete except for the 18” line connecting B-55 and B-56

  • Sidewalks along the east side of Central are complete to Broadway

  • Bump-out and added sidewalks at the SE corner of Broadway are complete

  • Roadway curb on NE corner of Broadway intersection is poured from Broadway to Regions Bank lower entrance

  • Signal foundations for poles A and D (5th Avenue) are complete

  • Planting soil has been placed from 4th to Broadway
     

TWO-WEEK LOOK AHEAD

  • Cross North Central and Dameron Place with new 18” storm and complete storm drainage line “B” (storm will be slightly more than 50% complete at this point)

  • Complete work on curbs and sidewalks surrounding Broadway intersection

  • Continue signal system work at 5th intersection and at Broadway
     

May 03, 2018

TRAFFIC CONTROL AND SAFETY

  •  Closure of Bearden Place this week between Central and Stewart Street while storm drainage is installed 18-0273, permit request for next week has been submitted and approved

  • Lane shift today and tomorrow on Broadway at North Central while new curbs and sidewalks are poured on northeast corner of the intersection 18-T-0317
     

 

PROGRESS SINCE APRIL 19, 2018

  • All 36” storm drainage is now installed, ending at STR. B-51

  • Asphalt has been patched from Broadway to Fulton Place

  • Sidewalks along the east side of Central from 3rd to bump out at Broadway have been poured

  • Signal foundation work at 5th Avenue has begun

TWO-WEEK LOOK AHEAD

  • Complete storm drainage in Bearden Place intersection

  • Continue work on curbs and sidewalks surrounding Broadway intersection

  • Continue signal system work at 5th intersection and at Broadway

  • Installation of planting soil to begin on 5/9/18
     

April 19, 2018

TRAFFIC CONTROL AND SAFETY

  •  Closure of Bearden Place between Central and Stewart Street requested for next week

  • COK has installed delineators in 5th to alert traffic to new design
     

 

PROGRESS SINCE APRIL 5, 2018

  • All storm drainage in the Broadway intersection is complete

  • Asphalt has been patched from Broadway to Fulton Place

  • Sidewalks along the west side of Central from 3rd to Broadway have been poured poured

  • Bump out and sidewalks along the east side of Central poured from 3rd approaching the antique store

  • Installation of the 36” storm has resumed and will be installed to structure B50.1 this week

  • Signal foundation at Broadway has been poured
     

TWO-WEEK LOOK AHEAD

  • Complete curbs and sidewalks from 3rd to Broadway

  • Install storm drainage in Bearden Place Intersection

  • Resume signal system work at 5th intersection and at Broadway

  • Begin installation of planting soil in planters that have been perc tested

April 05, 2018

TRAFFIC CONTROL AND SAFETY

  • Closure of Broadway intersection to install storm (TTCP 18-T-0191)

    • Broadway anticipated to be open by the end of the work day on Friday 4/6/18

    • Central will remain closed north and south of the Broadway intersection through next week

    • The outside right westbound lane of Broadway at Central will be closed through next week

 

PROGRESS SINCE MARCH 22, 2018

  • 18” storm installed from South of Broadway to across 3rd Avenue, from structure from 3rd Avenue to Central and Broadway

  • Curbs, gutter drains, and sidewalks from Regions Bank’s north entrance to Fulton Place have been poured

  • Floor for storm structure at the center of the Broadway intersection has been poured

  • Storm crossing Broadway, from the center of the intersection to the southwest corner has been installed using 16” ductile pipe

  • Storm crossing Central southbound lanes, from from the center of the intersection to the southeast corner has been installed

  • Storm crossing Central northbound lanes, from from the center of the intersection to the northeast corner has been is delayed by KUB conflicts

    • 16” ductile pipe used due to utility confines and elevation of existing 36” storm line

    • Water line conflict was resolved by KUB crews on 4/4/18

    • Gas line conflict will be addressed by KUB crews on 4/5/18 and 4/6/18

TWO-WEEK LOOK AHEAD

  • Complete storm drainage work in Broadway intersection

  • Construct curbs and sidewalks from 3rd to Broadway

  • Begin signal system work at 5th intersection and at Broadway

March 22, 2018

TRAFFIC CONTROL AND SAFETY

  • Closure of 3rd Avenue Thursday (March 22) and Friday (March 23) of this week to install storm pipe

  • Closure of 3rd Avenue Monday (March 26) and Tuesday (March 27) to install storm pipe

  • Closure of intersection of N Central and Broadway has been requested starting April 4 while the storm drainage is installed

 

PROGRESS SINCE MARCH 8, 2018

  • 36" storm installed from existing structure at Fulton Place just North of Magpies

  • 18" storm installed from just south of Broadway (at the antique store) to near 3rd Avenue

    • 3rd Avenue will be swept just south of Broadway to near 3rd Avenue

  • Work on west side curbs and sidewalks from 4th Avenue to Magnolia is complete

  • Bus shelter pad at Crafty Bastard has been poured

  • Work north of Broadway on curbs, sidewalks, and entrance to Regions Bank has begun
     

TWO-WEEK LOOK AHEAD

  • Complete all storm drainage work between 3rd Avenue and Broadway

  • Storm drainage work in the Broadway intersection starting  Wednesday, April 4, 2018

    • Temporary lane closures for potholing of utilities will occur from now to Wednesday, April 4

    • Full closure of intersection beginning Wednesday, April 4

    • Work will begin at the tie-in in the Broadway intersection and fan out from there, starting with the Broadway crossing first

March 08, 2018

TRAFFIC CONTROL AND SAFETY

  • Parking spaces along Central from 5th and 4th are ready to be opened as soon as work (by others) on 5th is complete.

  • There will be daily closure of Fulton Place through Monday, March 12 to install 36" storm pipe

 

PROGRESS SINCE FEBRUARY 22, 2018

  • Storm drainage installation across 5th Avenue is complete and asphalt in 5th is patched

  • 36" storm installed from existing structure at Regions Bank to the structure at Central Filling Station, and cross Fulton Place - progressed has been slowed by rock excavation

  • East side curbs, gutter pans, sidewalks and asphalt patching is complete to bump-out at 622 North Central (FM George)

  • Work on west side curbs and sidewalks from 4th Avenue to Magnolia has begun

  • Bus shelter pad at Crafty Bastard will be poured today
     

TWO-WEEK LOOK AHEAD

  • Continue installation of 36" storm line at the structure just north of Magpies

  • Complete curbs and sidewalks from 4th Avenue to Magnolia

February 22, 2018

TRAFFIC CONTROL AND SAFETY

  • Parking spaces along Central from 5th and 4th will remain barreled off until work is completed in this area

  • Asphalt patching will be complete by March 2nd and spaces will be re-opened

  • There will be a closure of Fulton Place on Friday, February 23 to install storm structure at this intersection

  • There will be daily lane closures on 5th Avenue on Monday, February 26 until 6pm Wednesday, February 28 to install storm drainage across 5th Avenue between N. Central Street and Williams Street

  • There will be daily closures of Fulton Place on Wednesday, February 28 through Friday, March 2 to install storm drainage across Fulton Place

 

PROGRESS SINCE FEBRUARY 8, 2018

  • KUB has corrected the utility conflicts at 5th Avenue and at the entrance to Regions Bank

  • 36" storm installed from existing structure at Regions Bank to the structure at Central Filling Station, and should be to Fulton Place by the end of this week

  • Curbs and sidewalks at the corner of 4th Avenue and N. Central are complete

  • Bus shelter pad at the corner of 4th Avenue is complete

TWO-WEEK LOOK AHEAD

  • Continue installation of 36" storm line at the structure across Fulton Place

  • Complete storm drainage installation across 5th Avenue

  • Work on curbs and sidewalks from 4th Avenue to Magnolia

  • Patch asphalt from 5th Avenue to 4th Avenue
     

February 08, 2018

TRAFFIC CONTROL AND SAFETY

  • Parking spaces along Central from 5th and 4th will remain barreled off until work is completed in this area

 

PROGRESS SINCE JANUARY 25, 2018

  • Storm pipe installed from 4th Avenue to 5th Avenue

  • All ADA ramps at the Magnolia intersection have been replaced

  • Asphalt has been patched from Depot to Magnolia

  • Work has begun for curbs and sidewalks at the corner of 4th Avenue and N. Central

TWO-WEEK LOOK AHEAD

  • Begin installation of 36" storm line starting at Regions Bank

  • Crossing of Regions Bank entrance will be scheduled for a weekend or at night
     

January 25, 2018

TRAFFIC CONTROL AND SAFETY

  • Parking spaces along Central from 5th and 4th will remain barreled off until work is completed in this area

TWO-WEEK LOOK AHEAD

  • Storm drainage next to Old Knoxville High School Senior Living facility and working from 4th Avenue to 5th Avenue

  • Sidewalk and curb replacement from Depot to Magnolia will be poured Week of January 22 (weather permitting)

  • Tactile warning replacement at Magnolia

  • Begin installation of 36" storm line at Regions Bank

  • Asphalt patching from Depot to East 4th Avenue (weather permitting)

January 11, 2018

Open house for North Central Street project stakeholders
WHEN: 5 - 6:30 p.m. Thursday, Jan. 11, 2018
WHERE: City of Knoxville Public Works Service Center, 3131 Morris Ave.
WHO: Representatives from the City of Knoxville, Amec Foster Wheeler construction engineering inspections services, Vaughn and Melton Civil Engineering firm, Southern Constructors Inc. general contractor, Hedstrom Design landscape architecture, and Central Street residents, merchants and property owners

TRAFFIC CONTROL AND SAFETY

  • Closure of North Central between Depot and Magnolia on Wednesday, Thursday, and Friday (week of 1/8/2018) to install storm drainage

  • Parking spaces along Central from 5th and 4th will be barreled off starting week of January 15, 2018

CURRENT PROGRESS

  • Project laydown yard located at 1008 Tyson Street

  • Inlet protection installed from West Depot Avenue to Dameron Avenue

  • Construction signs installed

TWO-WEEK LOOK AHEAD

  • Storm drainage next to Old Knoxville High School Senior Living facility and working towards 4th Avenue.

  • Sidewalk and curb replacement from Depot to Magnolia

  • Tactile warning replacement at Magnolia